SAP PS WBS Scheduling Parameters - SAP PS

How to schedule Parameters in WBS in SAP PS?

SAP PS facilitates in scheduling a project or a part of the project including the activities assigned to the project. SAP PS enables to use WBS element basic dates as basic dates for scheduling the activities.

Some of the activities which are not assigned to the same WBS, are considered as external networks in scheduling the project.

Step 1 − To define parameters for WBS scheduling, you can use T-code: OPTQ or you can navigate to SPRO → IMG → Project System → Dates → Data Planning in WBS → Define Parameter for WBS Scheduling.

OPTQ

Step 2 − In the next screen, click New Entries.

OPTQ New Entries

Step 3 − In the next window, you have to enter the following field −

  • Scheduling Type − To define type of scheduling.

Possible options are as shown in the screenshot given below.

Scheduling

Step 4 – Provide the following required information in the next screen as follows:

  • Start in Past − Enter number of past days when scheduling starts in past.
  • Scheduling Method − Select the scheduling method.
  • Reduction − To enter reduction lead time and reduction type and
  • Other fields as per business requirement.

Scheduling Type

Step 5 – After providing the details, the configuration need to be saved.

Data Save