MS Project Track Progress - Microsoft Project

What is MS Project Track Progress?

Once your project plan is ready in MS Project, it becomes necessary for a project manager to measure the actuals (in terms of work completed, reserves used and costs incurred) and to modify and change information about tasks and reserves due to any changes to the plans. A Project Manager should not suppose that everything is progressing according to plan and should always keep track of each task. Resistance to formal tracking of project management data is normal. You can surmount resistance to tracking by explaining your expectations, explaining the benefits of tracking, and training people to track the task themselves.

Save a Baseline

To appraise project performance you need to create a baseline against which you will compare the progress. One needs to save the baseline, once a plan is fully developed. Of course, due to rolling wave planning or progressive elaboration needed to manage projects one can always add new tasks, reserves, constraints and costs to the plan.
Also note, it makes sense to save the baseline before entering any actual values such as percentage of task completion.
Note − With MS Project 2013, you can save up to 11 Baselines in a Single plan. These multiple baselines seem contrary to the definition of baseline. You can use this flexibility when −
  • You have a baseline plan for the external customer and another for the internal team.
  • You are preparing for a risk event. You want to develop separate baseline plans for risk response and recovery.
  • You are accommodating a big change request, you might still want to keep the original plan for future reference when communicating with a stakeholder.

Create a Baseline

image 44

View Baseline on Gantt Chart

You will see Baseline Gantt bars displayed together with the current Gantt bars.
image 45

Update a Baseline

As time and work progresses on a project, you might need to change the baseline as well. You have several options for the same −
  • Update the baseline.
  • Updaate the baseline for selected tasks.
  • Save multiple baselines.

Update the Baseline for the Entire Project

This simply replaces the original baseline values with the currently scheduled values.

Update the Baseline for Selected Tasks

This does not affect the baseline values for other tasks or reserve baseline values in the plan.

Save Multiple Baselines

You can save up to 11 baselines in a single plan. The first one is called Baseline, and the rest are Baseline 1 through Baseline 10.
image 46

Interim Plans

An interim plan saves only two kinds of information for each task − Current start dates and Current finish dates.
It can be used as a project marker. It is visually easy to see how off-track or on-track the project progress is. Because it only specifies dates, it is simple, clear and easy information.
image 47

Track Plan by Specific Date

If all tasks have started and are complete as planned, you can record this in the Update Project dialog box. Most of the times, a seasoned project manager recognize that this isn’t true. But sometimes this advance might be fine when the actual work and cost values generated are close adequate to your baseline schedule.
image 48
Check marks will appear in the indicators column for tasks that have been completed. On the right in the Chart portion, progress bars are generated in the Gantt bars of each task.
image 49

Track Plan as % Complete

Method 1

image 50

Method 2

Now for the required Task, click the corresponding % Comp column and enter the required % complete.

Track Plan by Actual Values

You can enter the following actual values for your project −
  • Actual Start and finish dates - Project moves the schedule accordingly.
  • Task’s Actual duration - If equal or greater than schedule duration: task = 100% complete.

Task’s Actual Duration

You will see the % W. Comp. (% work complete) column.
This table includes Work (Scheduled work), Actual, and Remaining columns.
Click on Task you want to update. In the following example, Task 9’s Actual field is clicked and 24 hours is entered. For this task, initial planned Work was 16 hours, because 24 hours is greater. The project marks the task as 100% absolute and updates the Work column to 24 hours (from initial 16 hours). In the example, a Baseline is saved, because the Baseline does not change and is used as a evaluation. The Baseline is still at 16 hours and a Variance of 8 hours is now calculated by MS Project.
Note − Actual work is rolled up and also reflects on the summary task.
image 51

Actual Start and Finish Dates

Click Task whose dates you would like to change.
You can fill Actual duration field as well.
image 52