Selecting a Schedule - LoadRunner

You select the schedule you want to use for your manual scenario from the Scenario Name box in the Scenario Schedule pane. You can select one of the existing schedules Slow Ramp Up or Ramp Up or New Schedule, if you want to create a schedule with new properties using the Schedule Builder.

Note that you can also change the properties for one of the three existing schedules using the Schedule Builder.

To create a new schedule:

  1. Select <new schedule> from the Scenario Name box in the Scenario Schedule pane. The New Schedule dialog box opens.
  2. To create a new schedule

  3. In the Name text box, type the name of the New Schedule and click OK. The Schedule Builder dialog box opens.

To modify the properties of an existing schedule:

  1. Select Slow Ramp Up or Ramp Up from the Scenario Name box in the Scenario Schedule pane of the Design tab.
  2. Select Scenario > Schedule Builder, or click the Edit Schedule button. The Schedule Builder dialog box opens. To rename a schedule, click Rename. Enter the new name you want to use in the dialog box that opens. To delete a schedule, click Delete.
  3. To modify the properties of an existing schedule

Understanding the Schedule Builder Dialog Box

The Schedule Builder dialog box enables you to configure the schedule settings for the scenario.

Schedule Name: Select the name of the schedule you want to use for the scenario. Three default names appear: Default Schedule, Ramp Up, and Slow Ramp Up. Ramp Up increments the release of the Vusers at a relative pace. Slow Ramp Up increments the release of the Vusers at a slower pace. New: Opens the New Schedule dialog box, enabling you to enter the new schedule name.
Rename: Renames the schedule.

Delete: Deletes the schedule name.

Scenario Start Time: Opens the Delay Scenario Start dialog box, enabling you to start running a manual or goal-oriented scenario at a later point in time.

Schedule Definition

  • Schedule by Scenario: Defines the settings of the entire scenario.
  • Ramp Up Tab: Determines how to start the scenario.
  • Duration Tab: Sets the duration of the scenario.
  • Ramp Down Tab: Determines how to stop the scenario.
  • Schedule by Group: Defines an individual group’s settings. From the box on the left, select the Vuser group you want to schedule.
  • Start Time Tab: Determines how to set the start time for the Vuser group.
  • Ramp Up Tab: Determines how to start the Vuser group.
  • Duration Tab: Sets the duration of the Vuser group.
  • Ramp Down Tab: Determines how to stop the Vuser group.

Initialize all Vusers before Run: Instructs LoadRunner to initialize Vusers before beginning to load them. The ramping up of the Vusers begins only after all the Vusers reach the Ready status.

Load Preview: Displays a graph of the scenario schedule you defined. Note: Rendezvous points in a Vuser script interfere with a scheduled scenario. If your script contains rendezvous points, your scenario will not run as scheduled.